Vegas Loop Network
The Boring Company's Vegas Loop is operating and expanding under the resort corridor. Clark County approved 19 additional stations on August 25, 2026, bringing the entitled total to 123, and the Sahara Las Vegas station opened August 6, 2026.
- Owner
- The Boring Company
- Builder
- The Boring Company
- Reported cost
- Not disclosed
- Entitled stations
- 123 as of August 25, 2026
- Scope, company page
- 8 stations, more than 3 million passengers, 68 miles approved
- Scope, later reporting
- About 11 stations open, more than 10 miles of tunnel with roughly 4 miles operational, more than 4 million passengers
- Status
- Under construction
- Type
- Transit
Where it stands
On August 25, 2026 Clark County approved 19 additional stations, bringing the entitled total to 123 (Teslarati). The Sahara Las Vegas station opened August 6, 2026, with a Paradise Road entrance operating 7 a.m. to 9 p.m. (FOX5 Vegas).
The first City of Las Vegas building permit was issued January 28, 2026, opening the downtown expansion, and a 2-mile line from the Convention Center to north of Tropicana was under construction and set to open in 2026 (Las Vegas Review-Journal). Of the 123 entitled stations, roughly 11 are open, and only about 4 of more than 10 tunnel miles are in operation (Teslarati).
Approvals and public record
Clark County station approvals run through August 25, 2026, when 19 stations were added for a total of 123 entitled (Teslarati). The first City of Las Vegas building permit was issued January 28, 2026 (Las Vegas Review-Journal). The case numbers are not listed in the sources we have.
What is not known
No total capital cost or per-station cost for the network has been disclosed (The Boring Company). Two sets of scope figures also conflict: the company's own page cites 8 stations, more than 3 million passengers and 68 miles approved, while later reporting cites about 11 stations open, more than 10 tunnel miles with roughly 4 operational, and more than 4 million passengers (Teslarati). We print both and do not reconcile them.
The Fontainebleau station opening and the start of airport rides in December are recorded without a year in the source we have, and the case numbers for the county station approvals are not listed.
Why it matters
The gap between 123 entitled stations and roughly 11 open ones is the practical measure of the network: entitlement volume is far ahead of built capacity, and only about 4 tunnel miles carry passengers. For resort operators, each new station is a negotiated connection into private property, which is why the approval count moves faster than the tunnelling.
Timeline
- First city permit
The City of Las Vegas issued its first building permit, opening the downtown expansion.
- Sahara station opened
The Sahara Las Vegas station opened with a Paradise Road entrance.
- 19 more stations approved
Clark County approvals brought the entitled total to 123 stations.
- Convention Center line
A 2-mile line from the Convention Center to north of Tropicana was under construction and set to open.
Sources
- The Boring Company - Vegas Loophttps://www.boringcompany.com/vegas-loop
- Teslarati - Boring Company opens the Vegas Loop's newest stationhttps://www.teslarati.com/elon-musk-boring-company-opens-vegas-loops-newest-station/
- FOX5 Vegas - Sahara Las Vegas station now openhttps://www.fox5vegas.com/2026/08/06/vegas-loop-station-now-open-sahara-las-vegas/
- Las Vegas Review-Journal - first city permit for the Vegas Loophttps://www.reviewjournal.com/local/traffic/boring-co-receives-1st-vegas-loop-permit-from-city-opening-up-downtown-las-vegas-expansion-3612994/
Every figure on this page is attributed to a document or a published report. Where sources disagree we print both numbers rather than choosing one. Where the record is silent we say so.
Other transit projects
Planning a project of your own?
We cover this market for a living, which means we know what things actually cost right now, who is busy, and who is good. Tell us what you're planning and we'll point you toward independent licensed contractors who specialize in it — no cost, no obligation.
Tell us about your projectBuilding Las Vegas is a media company, not a contractor.