Athletics MLB Ballpark
The Las Vegas Athletics are building a 33,000-seat ballpark on the South Strip. The second of six roof truss arches was set during the week of August 20, 2026, with the remaining four scheduled for installation by the end of 2026.
- Owner
- Las Vegas Athletics
- General contractor
- Mortenson-McCarthy joint venture
- Architect
- Not disclosed
- Reported cost
- $2.0 billion total; about $400 million spent as of May 23, 2026
- Scope
- 33,000 seats
- Target completion
- Spring 2028 per the LVCVA bulletin; late February 2028 in reporting
- Status
- Under construction
- Type
- Stadium
Where it stands
During the week of August 20, 2026 the second of six roof truss arches was set, completing that installation (Las Vegas Review-Journal). The remaining four arches are scheduled for installation by the end of 2026 (Ballpark Digest).
The project was described as on schedule and on budget, with Mortenson-McCarthy as the general contractor (ESPN). About $400 million of the $2.0 billion cost had been spent as of May 23, 2026 (Ballpark Digest), and the LVCVA bulletin lists a 33,000-seat capacity and a Spring 2028 completion (LVCVA).
Approvals and public record
No dated case numbers for this project appear in the sources we have.
What is not known
Two completion dates circulate: the LVCVA bulletin lists Spring 2028 (LVCVA) while reporting cites late February 2028 (ESPN). We print both and do not reconcile them. The precise handover date is not stated in the sources we have.
Where the Athletics will play their 2027 home season is also not stated, no architect of record is named, and no dated case numbers were confirmed.
Why it matters
Four of six roof arches still have to be erected in roughly four months, which concentrates crane time, ironwork and inspection load on the South Strip through the end of 2026. The schedule is also the reference point for every adjacent Tropicana-corridor project that has to work around the same street closures.
Timeline
- Spend reported
About $400 million of the $2.0 billion budget had been spent, with the project called on time and on budget.
- Second roof arch complete
The second of six roof truss arches was set.
- Remaining arches scheduled
The four remaining roof truss arches are scheduled for installation.
- Completion listed
The LVCVA bulletin lists completion in spring 2028; reporting cites late February 2028.
Sources
- ESPN - Athletics Las Vegas ballpark roof milestonehttps://www.espn.com/mlb/story/_/id/49675850/
- Las Vegas Review-Journal - second roof arch completehttps://www.reviewjournal.com/sports/athletics/truss-the-process-2nd-as-las-vegas-ballpark-roof-arch-installation-complete-3865626/
- Ballpark Digest - August 25, 2026 milestonehttps://ballparkdigest.com/2026/08/25/new-vegas-as-ballpark-hits-milestone-ballys-resolves-planning-issues/
- Ballpark Digest - after $400M, on time and on budgethttps://ballparkdigest.com/2026/05/23/after-400m-new-athletics-ballpark-is-on-time-on-budget/
- LVCVA - Tourism Construction Bulletin, May 15, 2026https://res.cloudinary.com/simpleview/image/upload/v1779405036/clients/lasvegas/ConstructionBulletin051526_86c37e79-6dc1-4879-a2dd-e05ad92d28ca.pdf
Every figure on this page is attributed to a document or a published report. Where sources disagree we print both numbers rather than choosing one. Where the record is silent we say so.